Full text
Engelstein v. United States Department of Agriculture
[5] UNITED STATES DISTRICT COURT 6 WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
[7] DAVID ENGELSTEIN,
[8] Plaintiff,
[9] v. C20-0916 TSZ
[10] UNITED STATES DEPARTMENT ORDER 11 OF AGRICULTURE, et al., 12 Defendants.
13 THIS MATTER comes before the Court on Defendant United States of America’s 14 motion to dismiss for lack of subject matter jurisdiction, docket no. 124, and motion to 15 strike, docket no. 173. The Court having previously entered a Minute Order, docket 16 no. 175, granting the motion to dismiss and denying the motion to strike, now enters the 17 following order explaining its reasoning. 18 Overview 19 On June 18, 2017, Plaintiff David Engelstein was riding his bicycle on the Middle 20 Fork Road (the “Road”) in North Bend, Washington. Second Am. Compl. (“SAC”) at 21 ¶ 5.1 (docket no. 58); Ex. C to Johnson Decl. at 2 (docket no. 125-3). At the time of 22 Engelstein’s bike ride, the Road was under construction pursuant to the Middle Fork 1 Snoqualmie River Road Reconstruction Project (the “Project”). A portion of the Road 2 was constructed of grate panels. SAC at ¶ 5.1. Engelstein alleges that, while crossing
3 over the grate surface, he fell because his bike tire got wedged within a gap between the 4 grate panels and he sustained serious injuries. Id. at ¶ 5.2. 5 A. The Middle Fork Snoqualmie River Road Reconstruction Project 6 The Road is owned by King County (the “County”). See Ex. A to Johnson Decl. 7 at 2–6 (docket no. 125-1); Pl.’s Resp. Br. at 2 & 8 (docket no. 149). The Road was under 8 construction pursuant to a contract between the Federal Highway Administration
9 (“FHWA”), the United States Forest Service (the “Forest Service”), the County, and 10 Active Construction, Inc. (“ACI”). Following a study on the impact of paving the Road, 11 the FHWA, the Forest Service, and the County agreed to reconstruct approximately 12 9.7 miles of the Road. Id.; see also Ex. B to Johnson Decl. at 1 (docket no. 125-2), Ex. C 13 to Johnson Decl. at 1–3. The FHWA solicited bids for the Project and ultimately
14 awarded a contract for the Project to ACI (the “Contract”). Ex. D to Johnson Decl. at 1–2 15 (docket no. 125-4). 16 The Contract tasked ACI with constructing a 20-foot paved roadway, 17 reconstructing two bridges and replacing one bridge with a culvert, replacing numerous 18 existing roadway culverts, and upgrading signing and other roadside safety features.
19 Ex. B to Johnson Decl. at 1. The Contract also called for ACI to design, manufacture, 20 and install low water crossings. Ex. D to Johnson Decl. at 56–59; Ex. E to Johnson Decl. 21 at 1–49 (docket no. 125-5). Specifically, the Contract provided that ACI would design, 22 manufacture, and install “precast reinforced concrete box culverts and associated curb 1 headwalls, stem walls, and wing walls according to layouts and requirements shown on 2 the plans.” Ex. D to Johnson Decl. at 56. The work also consisted of “designing and
3 constructing three-sided concrete trench drains with removable steel grates according to 4 layouts and requirements shown on the plans.” Id. 5 When designing the low water crossings, the FHWA and ACI had to consider 6 certain regulations, administrative guidance documents, and policy manuals, many of 7 which served as non-mandatory guidance for the designers and engineers. See Exs. H–K 8 to Johnson Decl. (docket nos. 125-8–125-11). A separate agreement between the federal
9 agencies and King County stated that the low water crossings would be designed in 10 accordance with the American Association of Highway and Transportation Officials 11 (“AASHTO”) specifications. Ex. A to Johnson Decl. at 3. In addition, the Contract 12 incorporated the Standard Specifications for Construction of Roads and Bridges on 13 Federal Highway Projects (“Standard Specifications”), and it supplemented the Standard
14 Specifications with specific language tailored to the Project. Ex. D to Johnson Decl. at 15 29–32; Ex. G to Johnson Decl. (docket no. 125-7). The Standard Specifications required 16 contractors to “[p]repare drawings as necessary to construct the work[,]” furnish the 17 drawings “for acceptance before performing work covered by the drawings[,]” and 18 “[o]btain written approval before changing or deviating from the accepted drawings.”
19 Ex. G to Johnson Decl. at 17. The Contract supplemented the Standard Specifications by 20 identifying specific drawings that ACI was required to prepare and submit for the Project, 21 which included drawings for the low water crossings. Ex. D to Johnson Decl. at 35–37.
[22] 1 Prior to construction, ACI and its subcontractor, OldCastle Precast (“OldCastle”), 2 submitted design drawings for the low water crossings to the FHWA and the County for
3 approval. Ex. E to Johnson Decl. at 1–5. The FHWA, the Forest Service, and the County 4 approved these designs in June 2014. Id. In August 2014, Oldcastle and ACI submitted 5 additional drawings with additional detail regarding the grates, knowing that the 6 Washington Department of Transportation (“DOT”) would inspect them. Id. at 31–34. 7 The FHWA and the County approved the supplemental designs in August 2014. Id. at 8 35–49.
9 After the final design plans were approved, OldCastle manufactured, and ACI 10 installed, the low water crossings.1 The Contract provided that “at all times during 11 performance” of the Project “and until the work is completed and accepted, [ACI] shall 12 directly superintend the work or assign and have on the worksite a competent 13 superintendent who is satisfactory to the [FHWA] and has authority to act for [ACI].”
14 Ex. D to Johnson Decl. at 23. ACI was also responsible for obtaining its own permits, 15 licenses, materials, and equipment. Id. at 23. In addition, ACI agreed to assume all 16 responsibility for injuries arising as a result of its own negligence. Id. 17 The Standard Specifications contained provisions regarding construction of the 18 Project. Specifically, the Standard Specifications provided that ACI was required to
19 “[i]ndemnify and hold harmless the Government, its employees, and its consultants from
[20] 21 1 In a previous order, the Court dismissed plaintiff’s claims against ACI and OldCastle because they were joined as defendants after the three-year statute of limitations had expired and neither tolling nor relation22 back doctrines applied. Order at 9–10 (docket no. 90). 1 suits; actions; or claims brought for injuries or damage received or sustained by any 2 person, persons, or property resulting from the construction operations arising out of the
3 negligent performance of the contract.” Ex. G to Johnson Decl. at 36, § 107.05. In 4 addition, the Standard Specifications state that during “the performance of the contract, 5 the Contractor is an independent contractor and neither the Contractor nor anyone used or 6 employed by the Contractor shall be an agent, employee, servant, or representative of the 7 Government.” Id. at 37, § 107.09. The Standard Specifications also state 8 “[s]ubcontracting does not relieve the Contractor of liability and responsibility under the
9 contract and does not create any contractual relation between subcontractors and the 10 Government. The Contractor is liable and responsible for any action or lack of action of 11 subcontractors.” Id. at 39, § 108.02. 12 By June 2017, the time of Engelstein’s accident, the Project neared completion. 13 Construction was ongoing, although not on the grates at issue. On July 10, 2017, the
14 FHWA deemed the project substantially complete, and relieved ACI of its maintenance 15 responsibilities. Ex. C to Johnson Decl. at 1; Ex. F to Johnson Decl. at 1 (docket no. 12516 6). ACI finished work on the project in December 2017.2
[20] 21 2 The SAC is ambiguous as to whether ACI installed the grates at issue or whether the grates preexisted the construction. See SAC at ¶ 5.4. Regardless, in a June 30, 2023, status conference, the parties agreed 22 that ACI installed the subject grates prior to the accident. 1 B. Engelstein’s Claims 2 Engelstein asserts that the United States is liable for his injuries under the Federal
3 Tort Claims Act (“FTCA”).3 SAC at ¶¶ 4.6 & 6.1. Engelstein alleges that the United 4 States was negligent because the low water crossing grates were improperly constructed, 5 installed, and maintained, which led to his injuries. SAC at ¶ 5.3; Pl.’s Resp. Br. at 8. 6 Engelstein also appears to allege that the United States negligently approved the design 7 of the grates. SAC at ¶ 5.3; Nordstrom Report at 9 (docket no. 144-3) (“[T]he grate panel 8 gaps could not have been eliminated in the field either at the time of installation or after
9 the subject accident and were effectively ‘designed into’ the assembly.”). In sum, 10 Engelstein seeks to impose vicarious liability on the United States for a contractor’s 11 allegedly negligent construction, installation, and maintenance of the grates, and direct 12 liability for the United States’ negligent approval of the design for the grates. 13 The United States contends that this Court lacks subject matter jurisdiction under
14 the doctrine of sovereign immunity. Although the FTCA generally waives sovereign 15 immunity for negligence claims, the United States argues that sovereign immunity 16 applies in this case because of two exceptions to the FTCA’s waiver: the independent 17 contractor exception and the discretionary function exception.
[20] 3 The named federal defendants include the United States Department of Agriculture, United States Forest 21 Service, United States Department of Transportation, United States Department of Highways, United States Federal Highway Administration, and the Western Federal Lands Highway Division of the FHWA. 22 SAC at 1 & ¶¶ 2.1–2.5. This Order refers to the federal defendants collectively as the “United States.” 1 Discussion 2 A. The United States’ Motion to Strike
3 On July 31, 2023, Plaintiff filed a supplemental response, docket no. 171, to the 4 United States’ motion to dismiss, along with the Declaration of Greg Gebhard, docket 5 no. 170. The United States filed a motion, docket no. 173, to strike Plaintiff’s 6 supplemental response and the Gebhard Declaration pursuant to FRCP 12(f). Def.’s Mot. 7 to Strike at 1 (docket no. 173). The United States’ motion to strike, docket no. 173, was 8 previously denied by Minute Order, docket no. 175, for the following reasons. Motions
9 to strike are disfavored “and ‘should be denied unless the matter has no logical 10 connection to the controversy at issue and may prejudice one or more parties.’” Johnson 11 v. U.S. Bancorp, No. C11-02010, 2012 WL 6615507 , at *7 (W.D. Wash. Dec. 18, 2012) 12 (citation omitted). The Court considered Engelstein’s supplemental response because it 13 finally addressed in part the issues presented by the United States’ motion to dismiss.4
14 The Court also considered the Declaration of Greg Gebhard to the extent it 15 presents any admissible evidence. Although motions to strike under Rule 12(f) are
[16] 17 4 The United States filed its motion to dismiss on May 4, 2023, and the motion was originally noted for May 26, 2023. Engelstein requested additional time to complete discovery and to respond to the motion to dismiss. Pl.’s Mot. to Reset Discovery and Related Deadlines (docket no. 132); Notice of Mot.
[18] Renoted (docket no. 137). The motion to dismiss was renoted for June 16, 2023. Min. Entry (docket no. 138). On June 13, 2023, Engelstein filed a response to the motion to dismiss. Pl.’s Resp. Br. (docket 19 no. 149). Engelstein subsequently filed an additional motion for extension of time to complete discovery and a motion for additional time to further respond to the motion to dismiss. Pl.’s Mot. to Extend 20 Discovery Deadline (docket no. 152); Pl.’s Mot. for Extension of Time (docket no. 157). The Court permitted Engelstein to conduct additional depositions and to file a supplemental response. Min. Entry (docket no. 161). The motion to dismiss was renoted for July 28, 2023. Id. On July 31, 2023, Engelstein
[21] filed a supplemental response to the motion to dismiss. Pl.’s Supp. Resp. Br. (docket no. 171). In the supplemental response, Engelstein addressed for the first time whether ACI was an independent 22 contractor for purposes of the FTCA. 1 limited to pleadings, motions to strike materials that are not part of the pleadings can be 2 construed as an invitation “to consider whether the [proffered material] may properly be
3 relied upon.” Nat. Res. Def. Council v. Kempthorne, 539 F. Supp. 2d 1155 , 1161–62 4 (E.D. Cal. 2008) (citations omitted) (alteration in original). On numerous occasions in 5 his declaration, Gebhard qualifies his statement with phrases such as “I believe” or “it is 6 my understanding.” Gebhard Decl. at 2–4 (docket no. 170). Such statements raise 7 doubts as to Gebhard’s personal knowledge. Compare Milton H. Greene Archives, Inc. v. 8 CMG Worldwide, Inc., No. CV 05-2200, 2008 WL 11334030 , at *15 (C.D. Cal. Mar. 17,
9 2008) (“Declarations based on information and belief, rather than on personal knowledge, 10 are insufficient to create a genuine issue of material fact.” (citations omitted)), with 11 Edwards v. Toys “R” Us, 527 F. Supp. 2d 1197, 1201 (C.D. Cal. 2007) (noting that facts 12 alleged on belief or understanding do not create a genuine issue of fact but personal 13 knowledge “can be inferred from a declarant’s position with a company or business”).
14 Bearing this issue in mind, the Court considered the admissible portions of the Gebhard 15 Declaration and gave them the appropriate weight. 16 B. The United States’ Rule 12(b)(1) Motion 17 A Rule 12(b)(1) motion seeks dismissal of a claim for lack of subject matter 18 jurisdiction. See Fed. R. Civ. P. 12(b)(1). When responding to factual attacks on subject
19 matter jurisdiction,5 plaintiffs “must present ‘affidavits or any other evidence necessary
[21] 5 Here, the United States makes only a factual attack and does not assert a facial challenge to the Court’s 22 jurisdiction. 1 to satisfy [their] burden of establishing that the court, in fact, possesses subject matter 2 jurisdiction.’” Edison v. United States, 822 F.3d 510, 517 (9th Cir. 2016) (alteration in
3 original, quoting Colwell v. Dep’t of Health & Hum. Servs., 558 F.3d 1112, 1121 (9th 4 Cir. 2009)). The Court “may look beyond the pleadings to the parties’ evidence without 5 converting the motion to dismiss into one for summary judgment.” Id. (citing White v. 6 Lee, 277 F.3d 1214, 1242 (9th Cir. 2000)). When “evaluating the evidence, the court 7 ‘need not presume the truthfulness of the [plaintiff’s] allegations.’” Id. (quoting White,
[8] 277 F.3d at 1242 ). “Any factual disputes, however, must be resolved in favor of [the
9 plaintiff].” Id. (citing Dreier v. United States, 106 F.3d 844, 847 (9th Cir. 1996)). 10 The FTCA contains a “limited waiver of sovereign immunity, making the Federal 11 Government liable to the same extent as a private party for certain torts of federal 12 employees acting within the scope of their employment.” United States v. Orleans, 425
13 U.S. 807 , 813 (1976). Because suit can be brought against the United States “only to the
14 extent that it has waived its immunity,” courts must carefully heed exceptions to any such 15 waiver. Id. at 814. The United States’ assertion that, in this case, the independent 16 contractor and discretionary function exceptions deprive the Court of jurisdiction presents 17 threshold questions severable from the merits of the case, which are appropriately 18 decided under Rule 12(b)(1). Clemons v. United States, No. 2:21-CV-09194, 2022 WL 19 4596651, at *1 (C.D. Cal. July 7, 2022). Although Plaintiff has the burden of persuading 20 the Court that it has subject matter jurisdiction, “the United States bears the burden of 21 proving the applicability of one of the exceptions to the FTCA’s general waiver of
[22] 1 immunity.” Prescott v. United States, 973 F.2d 696, 703 (9th Cir. 1992). The Court 2 addresses each exception asserted by the United States.
3 a. Independent Contractor Exception 4 The independent contractor exception to the FTCA’s waiver of immunity bars 5 liability against the United States in instances where the conduct in question was 6 perpetrated by “any contractor with the United States.” 28 U.S.C. § 2671 . The United 7 States “cannot be held vicariously liable for the negligence of an employee of an 8 independent contractor.” Yanez v. United States, 63 F.3d 870, 872 (9th Cir. 1995)
9 (citations omitted). To determine if the independent contractor exception applies, courts 10 distinguish a federal employee from a contractor by evaluating “the existence of federal 11 authority to control and supervise the ‘detailed physical performance’ and ‘day to day 12 operations’ of the contractor.” Ducey v. United States, 713 F.2d 504, 516 (9th Cir. 13 1983); see also Carrillo v. United States, 5 F.3d 1302, 1304 (9th Cir. 1993); Autery v.
14 United States, 424 F.3d 944, 956 (9th Cir. 2005). A determination that the independent 15 contractor exception applies is not, however, the end of the analysis. Edison, 822 F.3d at 16 518. Courts must also evaluate “whether [the plaintiff] alleged a separate nondelegable 17 or undelegated duty, which the United States could be held directly liable for breaching.”
[18] Id. “Only upon a finding that the government delegated its entire duty of care may the
19 court dismiss the claim for lack of jurisdiction under the FTCA’s independent contractor 20 exception.” Id. (emphasis in original). The Court addresses whether the United States 21 may be held vicariously liable for ACI’s negligence or directly liable for breaching a 22 nondelegable duty. 1 i. Independent Contractor or Federal Employee 2 The United States argues that ACI was an independent contractor and that the
3 United States cannot be vicariously liable for ACI’s allegedly negligent construction, 4 installation, or maintenance of the low water crossing grates. The United States asserts 5 that it did not have “authority to control and supervise the ‘detailed physical 6 performance’ and ‘day to day operations’” of ACI.6 See Autery, 424 F.3d at 956 (quoting 7 Hines v. United States, 60 F.3d 1442, 1446 (9th Cir. 1995)); see also Ducey, 713 F.2d at 8 516. The United States may use detailed contractual provisions to “‘fix specific and
9 precise conditions to implement federal objectives’ without becoming liable for an 10 independent contractor’s negligence.” Autery, 424 F.3d at 957 (quoting Orleans, 425 11 U.S. at 816). “[D]etailed regulations and inspections are [not] evidence of an employee 12 relationship.” Id. (alterations in original, quoting Letnes v. United States, 820 F.2d 1517 , 13 1519 (9th Cir. 1987)). An individual may be deemed “acting as a government employee”
14 only if the United States exercised “substantial supervision over the day-to-day 15 operations of the contractor.” Id. (quoting Letnes, 820 F.2d at 1519 ). 16 Here, analogous cases teach that, given the structure of ACI’s and OldCastle’s 17 relationship with the FHWA, the two entities fall neatly into the categories of 18 independent contractor and subcontractor, respectively. See Clemons, 2022 WL 19 4596651, at *1–3 (describing the United States as forming contractor and subcontractor
[21] 6 Federal law determines whether ACI was an independent contractor or federal employee. Autery, 424 22 F.3d at 957 (citing Billings v. United States, 57 F.3d 797, 800 (9th Cir. 1995)). 1 relationships where the contractor was responsible for daily supervision of the 2 subcontractor’s janitorial services); Marcus v. United States, No. 96CV97, 1997 WL 3 1051847, at *1 (E.D. Va. May 29, 1997) (recommending dismissal based on the 4 independent contractor exception in a case involving a similar FHWA contract for road 5 resurfacing and a similar bicycle accident). In Marcus, the plaintiff was riding his 6 bicycle on a parkway, which was owned by the United States. 1997 WL 1051847 , at *1. 7 The plaintiff was injured when the bicycle’s front tire “slipped into an expansion joint” 8 between concrete slabs on a portion of the parkway that was under repair. Id. At the
9 time of the plaintiff’s bicycle accident, Century Concrete, Inc. (“Century”) was 10 resurfacing the parkway pursuant to a FHWA-awarded contract. Id. The plaintiff 11 asserted that Century created the dangerous condition during the resurfacing and that the 12 United States negligently failed to warn of the dangerous condition and allowed it to 13 continue. Id. Looking to the contract between the United States and Century, the court
14 determined that Century was not an agent or employee of the United States, and thus, the 15 United States was not liable for Century’s actions. Id. at *2–3. The court noted the 16 contract stated that “[a]t all times during performance of this contract and until the work 17 is completed and accepted, the Contractor shall directly superintend the work.” Id. at *1 18 (alteration in original). The contract also provided that Century was responsible “for
19 obtaining all permits and licenses, providing a safe work environment, and . . . all 20 materials delivered and work performed until completion and acceptance of the entire
[22] 1 project.”7 Id. at *3. Furthermore, the record contained no evidence or allegation that the 2 United States controlled Century’s day-to-day physical operations. Id. Thus, the court
3 concluded that it did not have jurisdiction. Id. 4 Similarly here, the Contract establishes that the United States was not responsible 5 for ACI’s day-to-day operations. Like the contract in Marcus, the Contract in this case 6 states that “[a]t all times during performance” of the Project “and until the work is 7 completed and accepted, [ACI] shall directly superintend the work or assign and have on 8 the worksite a competent superintendent who is satisfactory to the [FHWA] and has
9 authority to act for [ACI].” Ex. D to Johnson Decl. at 23. In addition, ACI was 10 responsible for obtaining its own permits, licenses, materials, and equipment. Id. at 23. 11 ACI also agreed to assume all responsibility for injuries arising as a result of its own 12 negligence.8 Id. Thus, as in Marcus, ACI was an independent contractor for, rather than 13 an agent or employee of, the United States.
14 In a supplemental response, Engelstein suggests ACI was not an independent 15 contractor because the United States was “intimately involved on a daily basis with
[16] 17 7 In the Background section, the Marcus Court pointed out that the contract between the United States and Century “contained an accident prevention clause which required Century to, among other things, ‘safeguard the public and government personnel, property, materials, supplies, and equipment exposed to
[18] Contractor operations and activities’ and ‘provide appropriate safety barricades, signs, and signal lights.’”
1997 WL 1051847 , at *1. The contract also provided that Century “would be ‘responsible for all 19 damages to persons or property that occur as a result of the Contractor’s fault or negligence.’” Id.
8 The Standard Specifications, which were incorporated into the Contract, provide that ACI was required 20 to indemnify the United States from suits brought for injuries or damage sustained as a result of negligent performance of the Contract. Ex. G to Johnson Decl. at 36, § 107.05. In addition, the Standard 21 Specifications explicitly state that ACI is an independent contractor for, and not an agent or employee of, the United States. Id. at 37, § 107.09. The Standard Specifications further provide that ACI is liable for 22 any action or inaction of subcontractors. Id. at 39, § 108.02. 1 managing the contractor’s performance in conformity with the Project contract.”9 Pl.’s 2 Supp. Resp. Br. at 7 (docket no. 171). Plaintiff’s argument is misplaced because nothing
3 in the record indicates that the United States substantially supervised ACI’s day-to-day 4 operations such that ACI was not an independent contractor. Although Engelstein points 5 out that the United States had a project engineer on site daily during construction, see 6 Traffalis Dep. at 24:5–9 & 60:18–24 (docket no. 162-2); Gebhard Decl. at ¶¶ 7–8 (docket 7 no. 170), the presence of federal employees does not establish that the United States 8 exercised substantial supervision over ACI’s physical performance of the contract. See
9 Hsieh v. Consol. Eng’g Servs., Inc., 569 F. Supp. 2d 159, 178 (D.D.C. 2008) (finding that 10 the federal government did not exercise detailed control or day-to-day supervision of a 11 contractor’s physical performance of a contract even though federal “personnel were out 12 ‘on the street’ every day,” and “performed routine inspections” because the contract 13 provided the federal government with the right the inspect the contractor’s work). As in
14 Hsieh, in this case, the record does not demonstrate that the federal government’s on-site 15 project engineer was there to manage ACI’s day-to-day operations such as how and when 16 to do the work. Instead, the federal government’s project engineer was on-site to ensure 17 ACI’s compliance with certain standards and the Contract itself, as required by the 18 separate agreement between the federal agencies and King County. See Ex. A to Johnson
19 Decl. at 6.10 In sum, the Contract provides that ACI was responsible for its own daily
[20] 21 9 Engelstein did not make this argument in his initial response. See Pl.’s Resp. Br. at 6 (docket no. 149). 10 The Forest Highway Project Agreement for Middle Fork Snoqualmie River Road stated: “During the
[22] construction phase of the project, [the Western Federal Lands Highway Division] will provide a Project 1 tasks and supervision. Ex. D to Johnson Decl. at 23. Indeed, ACI was responsible for 2 constructing, installing, and maintaining the grates that allegedly caused Engelstein’s
3 injuries. See Ex. E to Johnson Decl. at 33–49. Thus, the independent contractor 4 exception applies, sovereign immunity has not been waived, and the Court lacks 5 jurisdiction over Engelstein’s claim that the low water crossing grates were negligently 6 constructed, installed, or maintained. 7 ii. Nondelegable Duty 8 Notwithstanding ACI’s status as an independent contractor, the Court must
9 determine whether the United States may be held directly liable for breaching a 10 nondelegable or undelegated duty. Edison, 822 F.3d at 518 . Engelstein argues that the 11 United States is directly liable because it owed him a nondelegable duty of safety. Pl.’s 12 Resp. Br. at 7 (quoting Edison, 822 F.3d at 518 ); Pl.’s Supp. Resp. Br. at 1–2, 7. 13 “Whether the United States may be held liable under the FTCA for its own acts or
14 omissions is a three-step inquiry.” Edison, 822 F.3d at 519 . First, courts determine 15 whether state law “would impose a duty of care on a private individual in a similar 16 situation.” Id. (citations omitted). Second, if state law would impose such duty, courts 17 “then look to the contract and the parties’ actions to determine whether the United States 18 retained some portion of that duty for which it could be held directly liable.” Id.
19 (citations omitted). Third, “even if it appears that the government delegated all of its
[21] Engineer to oversee and inspect the work, and to ensure a quality product that meets all applicable 22 Federal, State and Local Standards and environmental requirements.” Ex. A to Johnson Decl. at 6. 1 duties to the independent contractor, we ask whether [state] law would impose any 2 nondelegable duties on the government.”11 Id. (citations omitted) (emphasis in original).
3 Engelstein cites the abnormally dangerous and/or peculiar risk exceptions to the 4 general rule that a principal is not liable for injuries caused by an independent 5 contractor.12 Pl.’s Resp. Br. at 4, 7, 13, 20, 22. In the alternative, Engelstein argues that 6 landowner-premises liability applies to this case, thus attaching a nondelegable duty of 7 safety. These exceptions do not apply to the facts of this case.13 8 First, under Washington law, the act of reconstructing a road or installing a low
9 water crossing is not an abnormally dangerous activity and does not pose a peculiar risk. 10 See Schuck v. Beck, No. 36754-1-III, 2020 WL 1922774 , at *5 (Wash. Ct. App. Apr. 21, 11 2020) (setting forth the six factors outlined in Section 520 of the Restatement (Second) of 12 Torts that should be considered in determining whether an activity is abnormally 13 dangerous and holding that transporting pressurized hazardous material to aid in the
[14] 15 11 The second step of the Edison analysis is not relevant in this case because the Court finds that the United States has delegated all of its duties to ACI regarding constructing, installing, and manufacturing 16 the grates. See Lentz v. United States Air Force, No. CV-17-1660, 2018 WL 3416993 , at *4 (D. Ariz. July 13, 2018) (finding that the second step of the Edison analysis was irrelevant after the court determined that the United States delegated all of its duties to an independent contractor). As in Lentz,
[17] however, the Court analyzes Engelstein’s claim that, under the third step of the Edison analysis, the United States should be held liable because Washington law imposes on it a nondelegable duty. See id.
[18] 12 “Under the FTCA, the United States may not be held vicariously liable. However, [peculiar risk] 19 liability has been construed as creating direct liability for the government's nondelegable duty to ensure that the contractor employs proper safety procedures.” Edison, 822 F.3d at 518 n.4 (alteration in original). Thus, where an employer has delegated some responsibilities to an independent contractor, the 20 employer may still be liable if the delegated responsibilities were “nondelegable” because the work performed is “inherently dangerous” or presents a “peculiar risk.” Id. at 518 & n.4. 21 13 Engelstein’s argument that AASHTO standards bind the United States to a nondelegable duty of safety is meritless. AASHTO is a private organization that promulgates industry best-practices—it does not 22 have the force of law. Engelstein’s argument sounds in a breach of contract analysis, not a tort analysis. 1 construction of a road was not an abnormally dangerous activity); see also Stout v. 2 Warren, 176 Wn. 2d 263, 273 , 290 P.3d 972 (2012) (setting forth the four factors to
3 consider in assessing whether an activity poses a peculiar risk); Hansen v. Horn Rapids 4 O.R.V. Park of the City of Richland, 85 Wn. App. 424, 433 , 932 P.2d 724 (1997) (stating 5 that “employment of emergency medical personnel does not involve a peculiar risk of 6 harm”). 7 Second, Engelstein does not argue that ACI and OldCastle performed the work in 8 an unsafe manner. Instead, Engelstein seeks to impose vicarious liability on the United
9 States for the allegedly negligent acts of the independent contractor and/or its 10 subcontractor. Unless, however, a contractor performs work in an unsafe manner, which 11 might lead to direct liability against the United States, the FTCA expressly precludes the 12 imposition of vicarious liability against the government for the actions of independent 13 contractors. See McCall v. U.S. Dep’t of Energy, 914 F.2d 191, 195 (9th Cir. 1990)
14 (rejecting argument that government can be held vicariously liable for negligence of 15 independent contractors under state-law “nondelegable duty” doctrine); Lentz, 2018 WL 16 3416993, at *4 (“Plaintiff’s argument fails to address the fact that state law cannot 17 preempt the FTCA if the state law imposes strict liability on the Government.” (citing 18 inter alia Bramer v. United States, 595 F.2d 1141 , 1144 n.7 (9th Cir. 1979))).
19 Finally, as to Engelstein’s premises liability theory, Engelstein describes a 20 nondelegable duty owed by a possessor of land under Arizona and California law. Pl’s 21 Resp. Br. at 20–22. This doctrine does not apply here because (i) the United States was 22 not a possessor of land—the County owns the Road; (ii) the duty in this case is governed 1 by Washington law, and Arizona and California law is inapplicable; and (iii) Arizona and 2 California law impose strict liability on the possessor of land for the harm caused by the
3 negligence of a contractor to maintain it safely, which cannot apply with respect to the 4 FTCA’s limited waiver of sovereign immunity. See Lentz, 2018 WL 3416993 , at *4. 5 The United States has thus carried its burden as to the independent contractor exception, 6 and the United States is entitled to dismissal for lack of subject matter jurisdiction. 7 b. Discretionary Function Exception 8 Engelstein appears to also or alternatively allege that the United States is directly
9 liable for his injuries because the United States negligently approved the design for the 10 low water crossings. The United States argues that its decisions about the low water 11 crossings are protected by the discretionary function exception to the FTCA’s waiver of 12 sovereign immunity. The discretionary function exception precludes liability for the 13 performance or nonperformance of “a discretionary function or duty on the part of a
14 federal agency or an employee of the Government.” 28 U.S.C. § 2680 ; see also Sabow v. 15 United States, 93 F.3d 1445, 1451 (9th Cir. 1996). The discretionary function exception 16 applies regardless of whether the government agent was negligent in his or her duties, so 17 long as those duties were discretionary. Kennewick Irrigation Dist. v. United States, 880
18 F.2d 1018 , 1029 (9th Cir. 1989). For the exception to apply, the challenged action must
19 be both (1) discretionary—i.e., not compelled by statute, policy, or regulation, and (2) the 20 type of action Congress meant to protect—i.e., an action that “involves a decision 21 susceptible to social, economic, or political policy analysis.” Whisnant v. United States,
[22] 400 F.3d 1177 , 1180–81 (9th Cir. 2005); see also United States v. Gaubert, 499 U.S. 315 , 1 322 (1991) (“The exception covers only acts that are discretionary in nature, acts that 2 ‘involve an element of judgment or choice.’”).
3 Here, the alleged conduct is discretionary—no statute, policy, or regulation 4 required the FHWA to adhere to a particular design for the low water crossings or 5 prohibited it from delegating design duties to an independent contractor. See Exs. H–K 6 to Johnson Decl.; see, e.g., Williams v. United States, 50 F.3d 299, 309 (4th Cir. 1995) 7 (“The regulations . . . do not prescribe a course of action, but impart to the United States 8 the discretion to exercise judgment and choice to contract for the maintenance of
9 premises it occupies.”) (cited with approval by Munger v. U.S. Soc. Sec. Admin., No. 10 C19-5571, 2020 WL 6874792 , at *2 (W.D. Wash. Nov. 23, 2020)). Although Plaintiff 11 argues that the AASHTO guidelines, incorporated by the Contract, mandated a particular 12 course of conduct, no statute, policy, or regulation required the FHWA to comply with 13 the AASHTO guidelines. The choice to follow AASHTO’s recommendations was itself
14 discretionary.14 The first prong of the discretionary function exception test is therefore 15 satisfied. 16 As to the public policy analysis element, a “strong presumption” exists that “the 17 second part of th[e] Gaubert test is satisfied if a court concludes that the employee was 18 exercising discretion,” A.O. Smith Corp. v. United States, 774 F.3d 359, 365 (6th Cir.
[19] 20 14 In any event, the AASHTO guidelines do not provide for a fixed, mandatory design for grates on a low water crossing. See, e.g., Nordstrom Report at 11, Ex. 3 to Notice (docket no. 144-3 at 12) (“The gap between the drainage grate and its frame should be 1 in. (25mm) or less.”). And, although a failure to
[21] follow the AASHTO guidelines might bolster a hypothetical negligence case against a defendant, that does not mean the AASHTO guidelines carry the force of law. They are no more than evidence of 22 industry best practices. 1 2014) (quoting Gaubert, 499 U.S. at 324 ), as the Court has concluded above. Ninth 2 Circuit jurisprudence, however, also requires the United States, in seeking to demonstrate
3 that the “discretionary function” exception applies, to identify “reasonable support in the 4 record for a court to find, without imposing its own conjecture, that a decision was 5 policy-based or susceptible to policy analysis.” Bear Medicine v. United States, 241 F.3d 6 1208, 1216 (9th Cir. 2001). Here, the United States relies on FHWA regulations that 7 supplement the agency’s policies concerning the National Highway System. See Defs.’ 8 Mot. at 23 (docket no. 124) (citing 23 C.F.R. §§ 625.3 (a)(1)(i)–(iv) (articulating, “in
9 addition to the criteria described in § 625.2(a),” four factors to consider in establishing 10 design and construction standards for highways: (1) the constructed and natural 11 environment of the area; (2) the environmental, scenic, aesthetic, historic, community, 12 and preservation impacts of the activity; (3) cost savings by taking advantage of 13 flexibility that exists in current design guidance and regulations; and (4) access for other
14 modes of transportation.) The United States also cites the FHWA’s publications 15 concerning (i) hydraulic design of highway culverts, and (ii) geomorphic, biological, and 16 engineering design considerations for low water crossings as evidence that the decisions 17 to install low water crossings, where to install them, what type to install, and/or how to 18 design them are policy-based or susceptible to policy analysis. See id. (citing Ex. H to
19 Johnson Decl. at 3, § 1.3.5; Ex. J to Johnson Decl. at 12–13). These materials support the 20 United States’ assertion that the second prong of the discretionary function standard is 21 satisfied. Further, as indicated by the United States, in determining whether low water 22 crossings are advantageous to the specific site, officials perform an economic evaluation, 1 which takes into consideration “all lifecycle costs including maintenance, repairs, user 2 costs, and the cost of environmental impacts.” Ex. J to Johnson Decl. at 11. ACI’s
3 request to redesign the grates from a diamond-pattern grate to a rectangular-pattern grate 4 exemplifies how the grate design involved or was susceptible to economic policy 5 analysis. See Ex. E to Johnson Decl. at 33–38. 6 The Project also involved a low-volume road on resource-sensitive public lands. 7 “These areas have significant and diverse stakeholders, regulations, management goals, 8 environmental resources, cultural resources, wildlife, scenic beauty and intrinsic value.”
9 Ex. I to Johnson Decl. at 5 (docket no. 125-9). Therefore, the technical work on the Road 10 had to embrace several key project delivery objectives including, but not limited to, being 11 respectful of the land, wildlife, and habitat, providing safe passage for travelers and 12 wildlife, minimizing impacts to existing features in a “lightly on land” manner, and 13 completing quality work within budget constraints, recognizing that funding is often
14 comparatively less for low-volume roads. Id. The FHWA had to consider all of these 15 goals when determining whether, where, and how to install the low water crossings. 16 Federal courts have determined that analogous considerations qualify as policy 17 determinations. See, e.g., Hager v. United States, No. 3:19-0673, 2020 WL 2544421 , at 18 *2 (S.D. W. Va. May 19, 2020) (concluding that the design, installation, maintenance,
19 operation, and lack of warning attending a culvert used to manage water runoff fell under 20 the discretionary function exception); E. Ritter & Co. v. Dep’t of Army, Corps of Eng’rs,
[21] 874 F.2d 1236 , 1241 (8th Cir. 1989) (design and construction of flood control ditch was 22 protected by the discretionary function exception). The Court sees no reason to depart 1 from the rationale in these cases. Both prongs of the discretionary function exception 2 having been met, the Court lacks subject matter jurisdiction over Plaintiff’s claim that the
3 United States negligently approved the design for the low water crossings. 4 Conclusion 5 For the foregoing reasons, the Court ORDERS: 6 (1) The United States’ motion to dismiss, docket no. 124, having been 7 GRANTED for the reasons set forth in this Order, Plaintiff’s claims against the United 8 States Department of Agriculture, United States Forest Service, United States Department
9 of Transportation, United States Department of Highways, United States Federal 10 Highway Administration, and the Western Federal Lands Highway Division of the 11 FHWA are hereby DISMISSED for lack of subject matter jurisdiction. 12 (2) Plaintiff and King County having reached a settlement, see Notice (docket 13 no. 176), Plaintiff’s claims against King County are DISMISSED with prejudice and
14 without costs, provided that Plaintiff may move within fourteen (14) days of the date of 15 this Order to reinstate his claims against King County in the event that the parties are 16 unable to perfect their settlement. 17 (3) Pursuant to Plaintiff’s “Motion to Dismiss Extraneous Defendants,” docket 18 no. 177, which is treated as a notice of voluntary dismissal, Plaintiff’s claims against the
19 unidentified and non-appearing defendants (Does I–X and S.E.A. Construction LLC) are 20 DISMISSED without prejudice. 21 (4) The parties having stipulated to dismiss Plaintiff’s claims against the State 22 of Washington, see Stipulation (docket no. 97), the Court having previously granted 1 summary judgment against Plaintiff and in favor of Active Construction, Inc. and 2 OldCastle Precast a/k/a Oldcastle Infrastructure, Inc., see Order (docket no. 90), and all
3 claims against all parties having now been resolved, the Court DIRECTS the Clerk to 4 enter judgment consistent with the Court’s rulings in this matter. 5 (5) The Clerk is further DIRECTED to send a copy of this Order and the 6 Judgment to all counsel of record. 7 IT IS SO ORDERED. 8 Dated this 11th day of September, 2023.
[9] A
[10] Thomas S. Zilly
[11] United States District Judge
