Full text
Cincinnati v. Pub. Util. Comm.
[6] OPINIONS OF THE SUPREME COURT OF OHIO
The full texts of the opinions of the Supreme Court of Ohio
are being transmitted electronically beginning May 27, 1992,
pursuant to a pilot project implemented by Chief Justice Thomas
J. Moyer.
Please call any errors to the attention of the Reporter’s
Office of the Supreme Court of Ohio. Attention: Walter S.
Kobalka, Reporter, or Deborah J. Barrett, Administrative
Assistant. Tel.: (614) 466-4961; in Ohio 1-800-826-9010. Your
comments on this pilot project are also welcome.
NOTE: Corrections may be made by the Supreme Court to the
full texts of the opinions after they have been released
electronically to the public. The reader is therefore advised to
check the bound volumes of Ohio St.3d published by West
Publishing Company for the final versions of these opinions. The
advance sheets to Ohio St.3d will also contain the volume and
page numbers where the opinions will be found in the bound
volumes of the Ohio Official Reports.
City of Cincinnati, Appellant, v. Public Utilities Commission of
Ohio et al., Appellees.
[Cite as Cincinnati v. Pub. Util. Comm. (1993), ___ Ohio St.3d
___.]
Public Utilities Commission — Conversion of nuclear power plant
to coal-fired facility — Application for rate increase —
Commission properly rejected equivalent plant standard for
valuing rate base, when — Owner-utilities’ decision to
convert to coal-fired facility found to be prudent, when —
Allowance for construction work in progress — Amended R.C.
4909.15(A)(1) pertains only to revenues collected after
April 10, 1985 — Court will not substitute its judgment for
that of the commission as to which of the fairly debatable
valuation periods is the most representative in determining
company’s cost of common equity.
(No. 92-2101 — Submitted June 2, 1993 — Decided November 3,
1993.)
Appeal from the Public Utilities Commission of Ohio, No. 91-410-
EL-AIR.
In 1969, intervening appellee Cincinnati Gas & Electric
Company (“CG&E”), Columbus Southern Power Company (“CSP”)
(formerly Columbus & Southern Ohio Electric Company) and Dayton
Power & Light Company (“DP&L”) entered into a joint venture to
construct the William H. Zimmer Nuclear Power Station (“Zimmer”).
On November 12, 1982, after numerous construction delays, the
Nuclear Regulatory Commission suspended all safety-related
construction at the site. By agreement dated January 20, 1984,
the joint owners canceled the Zimmer project as a nuclear plant
and agreed to use their best efforts to convert Zimmer to a coal-
fired facility. On August 1, 1984, they announced that Zimmer
would be converted to a 1,300 megawatt (“MW”) coal-fired plant.
On October 23, 1984, appellee, Public Utilities Commission
of Ohio (“the commission”), initiated In the Matter of the
Restatement of the Accounts and Records of The Cincinnati Gas &
Electric Company, The Dayton Power & Light Company, and Columbus
& Southern Ohio Electric Company, PUCO No. 84-1187-EL-UNC, to
determine the portion of the existing Zimmer investment which may
not be used and useful in a converted coal-fired plant and/or the
impact of imprudence or mismanagement, if any, on the level of
the Zimmer investment. On October 1, 1985, the parties to that
proceeding, except appellant city of Cincinnati (“the city”) and
the Board of Commissioners of Hamilton County, entered into a
stipulation which resolved that case. The stipulation generally
provided (1) that $861,000,000 of capital invested in the Zimmer
facility would be disallowed in the owner utilities’ future rate
cases; (2) that the investment remaining as of January 31, 1984,
i.e., the “remaining sunk costs” (including an allowance for
funds used during construction [“AFUDC”] properly accrued thereon
subsequent to January 31, 1984), would not be challenged by the
parties as being the result of mismanagement or as not being used
and useful in a Zimmer facility converted to coal generation; (3)
that the non-owner parties reserved the right to challenge the
reasonableness of any decision subsequent to the decision to
cancel construction of Zimmer as a nuclear plant in any future
proceeding before the commission; and (4) that the total Zimmer
investment that the owners could request to be included in a
future rate proceeding would be capped at $3.6 billion. The
commission unanimously approved the stipulation on November 26,
1985, after conducting a series of public hearings as to its
reasonableness, and upon consideration of the city’s testimony
and arguments opposing its adoption. The city did not appeal the
commission’s order.
Zimmer was successfully converted to a 1,300 MW coal-fired
plant at a total cost of $3.069 billion and has been providing
service since March 30, 1991. On April 2, 1991, the owner
utilities each filed an application to increase their rates for
electric service, in large part to receive a return on the
respective portion of their investment in Zimmer. CG&E
requested that its jurisdictional share of the facility be fixed
at $1,216,610,000. The city was granted leave to intervene in
CG&E’s rate case, and challenged CG&E’s proposed Zimmer
valuation.
By its order issued May 12, 1992, the commission reduced
CG&E’s requested rate-base allowance by $229,868,000,
specifically excluding improperly accrued AFUDC on the remaining
sunk costs, as well as nuclear-related costs deemed not used and
useful in the converted facility. (See the companion cases of
Cincinnati Gas & Elec. Co. v. Pub. Util. Comm. [1993], 67 Ohio St.3d 517 , 620 N.E.2d 821 , and Columbus S. Power Co. v. Pub.
Util. Comm. [1993], 67 Ohio St.3d 535 , 620 N.E.2d 835 , decided
this date.) The commission also rejected the city’s alternative
valuation proposals.
The cause is now before this court upon an appeal as a
matter of right.
__________________
Fay D. Dupuis, City Solicitor, and Richard Ganulin,
Assistant City Solicitor, for appellant.
Lee I. Fisher, Attorney General, James B. Gainer, Duane W.
Luckey, William L. Wright and Jeffrey D. Van Niel, Assistant
Attorneys General, for appellee.
Squire, Sanders & Dempsey, Alan P. Buchmann, Arthur E.
Korkosz and Lisa R. Battaglia; James J. Mayer and Michael A.
Gribler, for intervening appellee CG&E.
__________________
Per Curiam. The city argues that the commission erred: (1)
in determining Zimmer’s reasonable original cost, including
failing to make a prudence adjustment to CG&E’s Zimmer rate base;
and (2) in using a twelve-month average stock price to estimate
CG&E’s cost of common equity. For the reasons which follow, we
reject these arguments and affirm the commission’s order.
I. REASONABLE ORIGINAL COST
A. Equivalent Plant Standard
R.C. 4909.15 and 4909.051 require the commission to
ascertain the reasonable original cost of a utility’s used and
useful property for ratemaking purposes. In doing so in this
case for the converted Zimmer facility, the commission separated
the cost of the plant, in accordance with the 1985 stipulation,
into four distinct parts and included in rate base: (1) the sunk
costs remaining as of January 31, 1984, which were stipulated to
be used and useful in the converted coal-fired plant; (2) the
AFUDC properly accrued on the sunk costs; (3) the portion of the
post-cancellation conversion costs (i.e., the “going forward
costs”) determined to be used and useful in this proceeding; and
(4) the AFUDC on those costs. While the city concedes that the
commission properly determined the reasonableness of the used and
useful conversion costs and associated AFUDC in this proceeding,
it contends that the commission erred by not considering the
reasonableness of the otherwise allowable sunk costs. The
commission and CG&E generally contend that such a reasonableness
analysis of the remaining sunk costs is prohibited by the 1985
stipulation. We agree.
The stipulation was crafted to provide for a dollar
disallowance for “nuclear” Zimmer, rather than a consideration of
specific plant items, in order to accommodate settlement and to
avoid the need for an arduous “brick by brick” audit of specific
plant items. Accordingly, the stipulation does not distinguish
between the specific plant items deemed used and useful in a
converted Zimmer facility, and those which were included in the
$861 million disallowance. There being no means to identify or
challenge the pre-January 31, 1984 plant stipulated to be used
and useful in a converted Zimmer, it necessarily follows that the
stipulation prohibits inquiry into the “reasonableness” of these
otherwise allowable sunk costs. Indeed, in its 1985 order
approving the stipulation, the commission recognized that only
the reasonableness of the “going forward costs to complete the
converted [Zimmer] facility” were left open to challenge in the
instant proceeding. The city did not appeal that order and is now
bound by it.
Recognizing that the specific plant items represented by the
sunk costs are beyond review in this proceeding, the city based
its alternative Zimmer valuation (including the remaining sunk
costs and the conversion costs) upon the present value of the
allegedly comparable Rockport Power Plant in Indiana.2 The
commission rejected the city’s proposal as being contrary to the
original cost rate-base valuation required by R.C. 4909.05.
We have recognized that a utility’s rate base under the
original-cost standard is based upon the actual investment in the
assets of the utility. Babbit v. Pub. Util. Comm. (1979), 59 Ohio St.2d 81, 89-90 , 13 O.O.3d 67, 72 , 391 N.E.2d 1376, 1381 ;
Franklin Cty. Welfare Rights Org. v. Pub. Util. Comm. (1978), 55 Ohio St.2d 1, 11 , 9 O.O.3d 1, 6 , 377 N.E.2d 990, 997 . Clearly,
the city’s proposed Zimmer rate-base valuation, based upon the
cost of an allegedly comparable plant adjusted to price levels at
the time of valuation, violates the statutory original cost
standard and is unlawful under R.C. 4909.05(E).3
The city also argues that the AFUDC accrued on the remaining
sunk costs is not a “reasonable” cost of Zimmer and should be
excluded in its entirety from rate base. As set forth more fully
in the companion cases of Columbus S. Power, supra, and
Cincinnati Gas & Elec. Co., supra, the 1985 stipulation
explicitly provided for the allowance of such AFUDC in this
proceeding, subject only to its “proper accrual” under
established accounting conventions. Having determined in those
cases that the commission’s allowance of AFUDC on these sunk
costs from March 1986 until completion of the Zimmer facility was
neither unreasonable nor unlawful, we reject this argument.
Accordingly, we conclude that the commission properly
rejected the city’s equivalent-plant standard for valuing rate
base and that it properly determined Zimmer’s valuation within
the constraints imposed by the 1985 stipulation.
B. Prudence
While the 1985 stipulation prevented inquiry into the
reasonableness of the remaining sunk costs, it expressly left
open to challenge in this proceeding whether the owner-utilities’
decision to convert Zimmer to a coal-fired facility was prudent.
We adopt the commission’s definition of a prudent decision,
which is in accord with that used in other jurisdictions,4 as
“one which reflects what a reasonable person would have done in
light of conditions and circumstances which were known or
reasonably should have been known at the time the decision was
made.” In the Matter of the Investigation into the Perry Nuclear
Power Station (Jan. 12, 1988), PUCO No. 85-521-EL-COI, at 10-11.
The standard contemplates a retrospective, factual inquiry,
without the use of hindsight judgment, into the decisionmaking
process of the utility’s management. See Re Syracuse Home Util.
Co. (Dec. 30, 1986), PUCO No. 86-12-GA-GCR; Re Toledo Edison Co.
(July 16, 1987), PUCO No. 86-05-EL-EFC.
The issue central to the prudence inquiry below was whether
CG&E, in 1984, could have written off its entire Zimmer
investment and still have had sufficient access to the capital
markets to enable it to construct an arguably less costly
generating facility in time to meet its customers’ forecasted
energy needs in 1991. The construction options under
consideration included, inter alia, building a coal-fired plant
at a new (“greenfield”) site or adding an additional coal-fired
generating unit at an existing facility, owned by CG&E and DP&L,
at East Bend, Kentucky.
Although the commission found that CG&E’s decisionmaking
process was “less than adequate,” and made a corresponding
downward adjustment to the company’s rate of return, it refused
to make a prudence adjustment to CG&E’s Zimmer rate base.
Specifically, the commission found that an adjustment was not
warranted because the rate-base exclusions related to AFUDC,
nuclear fuel, and nuclear wind-down costs (nearly $230 million in
this case), as well as the $861 million disallowance required by
the 1985 stipulation (approximately $400 million in this case),
reduced Zimmer’s valuation to the range of costs to construct an
alternative plant at a greenfield site. Further, it found that
the East Bend option was not a viable alternative, primarily
because CSP did not own an interest in the site and also because
CG&E’s abandonment of its contractual obligation to pursue
construction at Zimmer could have resulted in costly and
extensive litigation, the outcome of which would be uncertain.
By this appeal, the city argues that East Bend was a viable,
lower-cost alternative to Zimmer’s conversion, that a prudent
utility manager would have selected that option over conversion
of the nuclear facility, and that the Zimmer rate-base valuation
should be reduced to the East Bend unit’s cost of construction.
The narrow question presented, whether East Bend is a viable
alternative, is one of fact. On questions of fact, this court
will not reverse an order of the commission absent a showing that
it is manifestly against the weight of the evidence, and is so
unsupported by the record as to show misapprehension, mistake, or
willful disregard of duty. MCI Telecommunications Corp. v. Pub.
Util. Comm. (1988), 38 Ohio St.3d 266, 268 , 527 N.E.2d 777, 780 .
We begin our review by noting that, having embarked on a
joint venture to construct the Zimmer nuclear facility, the owner-
utilities could not have considered the alternatives to
completion of that facility in a vacuum. It is undisputed on the
record in this proceeding that, in 1984, the joint owners
collectively needed the 1,300 MW of electricity that a converted
Zimmer facility would provide to meet their customers’ forecasted
energy needs in 1991.5 Obviously, had any one of the owner-
utilities unilaterally abandoned its Zimmer commitment,
protracted litigation could have followed, which, as it pertains
to this issue, could not only have affected CG&E’s financial
ability to pursue the East Bend option but, just as important,
could have prevented completion of that facility in time to meet
its customers’ forecasted energy needs.
The city argues that CG&E could have completed an East Bend
facility in 1991 to replace the capacity that otherwise would
have been provided by the converted Zimmer facility. It relies
on the testimony of its expert financial witness that it was
feasible for the company to accelerate completion of the East
Bend unit from 1998 (as assumed by a study conducted by the First
Boston Corporation for CG&E) to 1991. However, the witness’s
testimony addressed only the financial feasibility of
accelerating construction and admittedly did not take into
consideration the company’s capacity needs for the 1980s and
1990s, or the engineering, contractual and legal impediments to
selecting that site. CG&E’s witness testified that, assuming
these barriers were overcome, and even assuming the absence of
financial constraints in constructing a unit at East Bend, the
unit could not have been placed in service until 1995 or later
due, in part, to state (Ohio and Kentucky) and federal licensing
and permitting requirements.
The city also argues that sufficient blocks of power could
have been purchased from other utilities and were available for
1991 to meet CG&E’s customers’ energy needs until the East Bend
unit was placed into service. However, the city’s witness on
this issue admitted that his conclusion, based on 1991
forecasted data, relied upon hindsight judgment and was not
intended as a part of a prudence analysis of what the utilities
knew or should have known at the time the decision to convert
was made. According to the company’s analyses and the analyses
of the commission’s staff, based upon data available at the time
the decision to convert was made, such large amounts of bulk
power had an uncertain availability for the 1990s and beyond due
to existing low reserves in surrounding regions, the anticipated
curtailment of generation expansion and the effects of acid rain
legislation.6
We find that the record supports the commission’s
determination that the East Bend option was not a viable
alternative to Zimmer’s conversion and reject the city’s
proposition of law.
C. CWIP Offset
Between 1980 and 1983, the commission granted CG&E an
allowance for construction work in progress (“CWIP”) related to
Zimmer’s construction as a nuclear facility. There is no dispute
that these allowances were lawful under then-existing R.C.
4909.15(A)(1), or that they were collected by CG&E by April 11,
1983.
The city argues that the commission erred by not using these
lawfully authorized and lawfully collected revenues to offset
CG&E’s rate base in this proceeding. While R.C. 4909.15(A)(1)
was amended in 1985 to provide for such offsets, it pertains only
to revenues collected after April 10, 1985. Am.Sub.S.B. No. 27,
140 Ohio Laws, Part I, 58. There being no authority to offset
the revenues in question, we reject the city’s argument.
II. RATE OF RETURN
The issue presented by the city’s final proposition of law
is whether it was reasonable for the commission to use CG&E’s
average test-year stock price, as recommended by its staff, in
determining CG&E’s cost of common equity and, ultimately, its
overall rate of return.7 The city points to the rise in CG&E’s
stock price during the second half of 1991 and argues that the
first six months’ data is unrepresentative of current market
trends and conditions. It argues that either the six-month or
twelve-month average as of the issuance of the commission’s May
12, 1992 order is more representative and should have been
adopted by the commission. The commission found that the city’s
recommendation was based upon post-record data and refused to
adopt it. We find the commission’s determination to be neither
unreasonable nor unlawful.
Alternatively, the city argues that the six-month average as
of the close of hearing in mid-February 1992 should have been
adopted as being more representative. The commission rejected
the various short-term valuation periods (ranging from one to six
months) recommended by the experts testifying on this issue,
noting that it traditionally uses a twelve-month average in order
to minimize the effects of short-term market fluctuations.
Finding no anomalous conditions (e.g., a stock price break or
market break) which would make the twelve-month average
unrepresentative in this proceeding, the commission adopted its
staff’s recommendation.
We refuse to substitute our judgment for that of the
commission as to which of the fairly debatable valuation periods
is the most representative in determining the company’s cost of
common equity. See AT&T Communications of Ohio, Inc. v. Pub.
Util. Comm. (1990), 51 Ohio St.3d 150 , 555 N.E.2d 288 ; Cleveland
Elec. Illum. Co. v. Pub. Util. Comm. (1976), 46 Ohio St.2d 105 ,
75 O.O.2d 172 , 346 N.E.2d 778 . The commission’s determination,
based upon its staff’s recommendation, is supported by the record
and is neither unreasonable nor unlawful. Accordingly, we affirm
the decision of the commission on this issue.
Order affirmed.
Moyer, C.J., A.W. Sweeney, Douglas, Wright, Resnick, F.E.
Sweeney and Pfeifer, JJ., concur.
FOOTNOTES:
1. R.C. 4909.15(A)(1) requires the commission, in fixing rates,
to determine “[t]he valuation as of the date certain of the
property of the public utility used and useful in rendering the
public utility service for which rates are to be fixed and
determined. The valuation so determined shall be the total value
as set forth in division (J) of section 4909.05 of the Revised
Code.* * *”
R.C. 4909.05(J) provides that the valuation of a utility’s
property shall include the original cost of long-term assets
(R.C. 4909.05[C], [D], [E], [F], and [G]) less depreciation and
contributions of capital (R.C. 4909.05[H] and [I]). The Zimmer
investment at issue falls under R.C. 4909.05(E), which provides
that the “original cost” of such property “shall be the cost, as
determined to be reasonable by the commission, to the person that
first dedicated the property to the public use and shall be set
forth in property accounts and subaccounts as prescribed by the
commission.* * *”
2. The city also alleges that the commission used such an
“empirical benchmark,” albeit an erroneous one, in determining
Zimmer’s valuation. While the commission considered the cost to
construct an alternative plant, it did so in the context of
determining whether a further rate-base adjustment should be made
when considering the prudence of CG&E’s decision to convert, not
in considering whether the specific costs to construct Zimmer
were reasonable.
3. Three general methods are recognized in valuing utility
property: (1) original cost, which values existing plant and
additions based upon the actual cost to the person that first
dedicated the property to the public use; (2) reproduction cost
new (“RCN”), which values existing plant and additions at the
estimated price levels prevailing at the date of valuation; and
(3) fair value, which considers a property’s original cost and
current value, sometimes assigning weights to the two. See
Phillips, The Regulation of Public Utilities (2 Ed.1988) 304,
324; Priest, Principles of Public Utility Regulation (1969) 140-
141; Rose, Confusion in Valuation for Public Utility Rate-making
(1962), 47 Minn.L.Rev. 1. The city’s alternative valuation is
more akin to the RCN standard, which was formerly prescribed by
Ohio statute, but which has been replaced by the original cost
standard in 1976. See Babbit, supra,
59 Ohio St.2d at 89 , 13 O.O.3d at 72 , 391 N.E.2d at 1381 .
4. See Phillips, The Regulation of Public Utilities (2 Ed.1988)
326.
5. CG&E’s share of the converted Zimmer is approximately 600
MW, DP&L’s share is approximately 325 MW, and CSP’s share is
approximately 375 MW.
6. The city also points to other references in the record as to
the availability of purchased power. Specifically, it argues
that American Electric Power Corporation (CSP’s parent) had
arranged to provide CG&E with backup power; however, that offer
was made as a part of the January 20, 1984 agreement to convert
Zimmer and extended only during the term of Zimmer’s
construction. The city also points to a power sale proposal from
the Tennessee Valley Authority; however, the record does not
reflect that the proposal would satisfy the amount or duration of
power needed by CG&E, not to mention the needs of the other
owners. Finally, the city notes three other power sales in the
region executed in 1981, 1987 and 1990. Of course, the 1981 sale
could not be considered as available for CG&E and the other
owners at the time the decision to convert was made, and the
availability of the latter two are based upon a hindsight
analysis. None provided the amounts of power needed as a Zimmer
replacement.
7. In determining the cost of common equity, the commission
customarily, as here, employs the discounted cash flow (“DCF”)
model which, generally stated, estimates the required cost of
common equity by adding the current dividend yield (dividend
divided by representative stock price) and expected dividend
growth rate.
